Project Process of Park Project in Qatar
• In July 4th, we received the inquiry from our customer who sent us some client feedback picture.
• In July 5th, Beston started to communicate with our customers’ designer about the 2D park planning.
• In July 14th, the 2D park layout was finally confirmed with our customers in Qatar.
• In July 15th, we received the intention money for the design fee and started the 3D indoor park design.
• In July 25th, the 3D design of indoor fun center was eventually confirmed after six cycles of design and modification.
• In July 29th, Beston and our customer in Qatar signed the contract and confirmed the order.
• After receiving the advance payment in August 1st, we began the production until August 22nd.
• The delivery is completed on August 23rd, and the goods arrived at the port and complete the custom clearance around September 20th. And all three containers arrived on September 25th.
• The installation guidance and on-site installation of indoor soft playground for sale were mainly in October and November.